I am behind on updates for our remodeling project. Life got in the way of blogging as we gave Meggan a bedroom makeover, went on vacation and worked at Worship Arts Camp at our church. My schedule is open today, so I am catching up on some things.
progress summary
weeks 7-8: electrical in the new kitchen, cabinets installed, appliances delivered, Meg's room makeover
weeks 9-10: counter top installation, building/framing the new family room on back, wood floor delivered (vacation/work at church)
week 11: new family room shingled and windows installed, trim delivered, appliances and sink working, old kitchen cabinets removed, wall between piano room and dining room removed